QUESTIONA mechanic treats a corroded aluminum surface with chromic acid inhibitor. By when must the regular paint finish be applied over the treated surface?
- ANo later than 7 days afterward
- BNo later than the same day
- CWithin 72 hours of the treatment
Show the answer and explanation
Correct answer: B. No later than the same day
- A — incorrect A week is far beyond the stated limit, which ends on the day the chromic acid treatment is applied.
- B — correct The treatment must be followed by regular paint finishes as soon as practicable, and never later than the same day as the latest chromic acid treatment.
- C — incorrect No 72-hour allowance is given; leaving the treated surface unpainted past that day exceeds the handbook's limit.